Current State of Dacy Business Park (6/18/24)
Share
Take an aerial tour of Dacy Business Park as of June 18, 2024! Our latest flyover captures the progress on-site, showing all the building pads taking shape. Select fill is complete on 5 of the 13 pads.
Key Points:
- Select Fill Importance: Proper grade and moisture content in select fill are crucial for stability. We used soil injection to stabilize the ground, followed by 3 feet of select fill in 12" lifts, each tested to meet geotechnical standards.
- Detention Pond: The retaining wall around the pond is 90% complete, and work has started on the outfall.
- Subcontractor Meeting: We held a meeting with all key subs (electrical, plumbing, concrete, erectors). 4E Construction, our General Contractor, ensures smooth communication and coordination. All subs are licensed and experienced in similar projects, making them the backbone of this successful project.
Contact Us:
For more information, visit www.dacybusinesspark.com or contact Sam Lee at 512-577-8088 or sam@dacybusinesspark.com.
Keywords:
Dacy Business Park, commercial construction, select fill, soil stabilization, geotechnical engineering, detention pond, construction management, 4E Construction
Stay tuned for more updates!