Buildings are going vertical !
Our dedicated crews are making incredible progress at Dacy Business Park, even in the face of 100°F+ temperatures. Over the past two weeks, all three building pads have been successfully poured. To avoid overheating and potential cracks, our team began pouring concrete at 3:00 AM, taking advantage of cooler morning temperatures. Thanks to 4E's efforts in keeping the pads cool by spraying them with water, we’re maintaining the integrity of the slabs.
Exciting developments are underway as building erection has commenced. You can now see the metal frames rising from the foundations. Additionally, today we witnessed the installation of septic tanks, carefully lowered into place by crane. Ongoing work on the fire line, wastewater systems, and forced main for the septic system is also progressing smoothly.